GCC guide

GCC 2015 claim notices: clause 10.1 and the 28-day time bar

How to claim time or money under GCC 2015 clause 10.1, covering the 28-day written claim notice, detailed particulars, the Engineer's ruling and late notice.

Published 22 Oct 20264 min readClauses 10.1, 10.1.1, 10.1.2, 10.1.5All guides

What clause 10.1 is for

Clause 10.1 of the SAICE General Conditions of Contract for Construction Works, 3rd edition (GCC 2015), is the general route for any claim for an extension of time or additional payment. Whatever the ground (a late drawing, a variation, unforeseen ground conditions), the procedure here governs how and when you claim.

The procedure has two deadlines and a decision. You give a written claim notice within 28 days. You deliver detailed claim particulars within a further 28 days. The Engineer then gives a ruling.

Check which edition your contract uses before relying on anything below. GCC 2010 and GCC 2015 number their claim clauses differently. See our GCC overview.

Step 1: the written claim notice (clause 10.1.1)

Under clause 10.1.1, if you consider yourself entitled to an extension of time or additional payment, you must deliver a written claim notice to the Engineer within 28 days of becoming aware of the circumstances giving rise to the claim. The period runs from awareness, not from when you finish costing the effect.

The notice should state:

  • the circumstance relied on and the clause that gives the entitlement
  • the date you became aware of it
  • the extension of time or amount claimed, as far as you know it yet
  • the records you are keeping to support the claim

You do not need final figures at this stage. A short, clear notice sent on time is worth more than a complete one sent late. Address it to the Engineer and deliver it in the way the contract requires for notices.

Step 2: the detailed claim particulars (clause 10.1.2)

Clause 10.1.2 requires you to deliver the detailed claim particulars to the Engineer within 28 days after delivering the notice. The particulars set out the full basis of the claim: the facts, the contractual grounds, the time and money claimed, and the supporting records.

If the effects of the event are still continuing, the standard edition provides for interim particulars at regular intervals and final particulars once the effects end. Keep updating the claim rather than waiting for the event to finish.

Step 3: the Engineer's ruling

Once the Engineer has the particulars, the standard edition requires a ruling on the claim within a fixed period, normally 28 days. The Engineer may ask for more information first.

If you do not accept the ruling, the contract's dispute provisions set their own notice periods. Those are separate time bars, so diarise them as soon as the ruling arrives.

Step 4: what happens if the notice is late (clause 10.1.5)

Clause 10.1.5 sets out the consequence of not complying with the notice requirement. Under the standard edition, a contractor who fails to give the written claim notice in time is not entitled to the extension of time or additional payment claimed.

What missing the time bar costs: you can lose the whole entitlement to the time and money for that event, even where the event itself was the Employer's risk.

Late or incomplete particulars are treated differently from a late notice in the standard edition, but do not rely on that. Meet both deadlines.

Worked example with dates

GCC 2015 counts calendar days, so weekends and public holidays count. In this example we assume the contract does not move a deadline that falls on a weekend or public holiday.

  1. On Monday 2 March 2026 the site agent finds that the Employer's access road to a work area is still closed, contrary to the programme. This is the date the contractor becomes aware.
  2. Day 1 is Tuesday 3 March. Day 28 is Monday 30 March 2026. The written claim notice must reach the Engineer by then. Human Rights Day (21 March) falls on a Saturday in 2026 and is counted like any other day.
  3. The contractor delivers the notice on Friday 27 March 2026, three days early.
  4. The particulars are due 28 days after delivery of the notice, which is Friday 24 April 2026. Good Friday (3 April) and Family Day (6 April) fall inside this period and count as ordinary days.
  5. If the particulars are delivered on 24 April and the Engineer's period is 28 days, the ruling would fall due on Friday 22 May 2026.

Had the notice gone in on Tuesday 31 March, it would have been one day late.

Practical points

  • Start the clock on the day someone on site knew, not the day the office heard about it.
  • Send the notice first and gather the evidence after. The particulars are for detail.
  • Keep contemporaneous records (site diaries, photos, labour and plant returns) from day one, and say in the notice that you are keeping them.
  • Get written proof of delivery to the Engineer.

Your contract may differ

This guide describes the standard GCC 2015 conditions. The signed contract's own amendments, particular conditions and contract data govern over the standard text. Check them for changed periods, a different addressee or extra notice requirements. This guide is general information, not legal advice. For advice on a specific claim, speak to a construction lawyer or claims consultant.

What Sakhani does about this

Sakhani reads your signed contract, including its amendments, and records the claim periods that apply. When you log an event, it counts the days from the date of awareness, reminds the people responsible before each deadline and drafts the written claim notice for a person on your team to check and send. See how it works or register to try it.

A guide, not legal advice. It describes the standard, unamended conditions; the data, particular conditions and amendments of your signed contract govern, and the amounts at stake may call for your attorney or quantity surveyor. Reviewed by the Sakhani team before publishing.

Every GCC notice, counted from the day it starts.