When a JBCC 6.2 contractor must give notice of delay, how the 20 working days are counted, what the notice and claim must contain, and what lateness costs.
Under the JBCC Principal Building Agreement 6.2 (2018), a delay does not earn you more time on its own. You must tell the Principal Agent in writing, within a fixed number of working days, and then follow up with a properly supported claim. This guide covers both steps.
When you become aware of a delay you believe entitles you to more time, such as late or incomplete construction information, clause 23.4.2 read with clause 23.5 requires a Notice of intention to claim to the Principal Agent. It must reach the Principal Agent within 20 working days of the date you became aware of the circumstance. The clock does not wait for the delay to end or for you to know its full cost.
The entitlement can cover both time (a revision of the date for practical completion) and cost. Both depend on the notice going in on time.
JBCC counts working days, not calendar days. In general that means Monday to Friday, excluding South African public holidays and the builders' year-end break. Check the definition in your signed agreement and whether Saturdays are working days on your project.
The count starts from the date you became aware, not the date the problem first existed. Day one is the next working day. If you are unsure exactly when you became aware, count from the earliest date you could reasonably be said to know.
Keep it factual and complete. Include:
You do not need final figures at this stage. A short notice sent on time is worth more than a detailed one sent late.
The notice is followed by the Claim for revision of the date for practical completion under clause 23.5, with the particulars: the working days claimed, a programme showing the effect on the critical path, and any cost. The edition allows 40 working days for this, counted from when the delay ceased, not from the notice.
Where a delay is still running, it is sensible to submit interim particulars rather than wait. Many contractors also work to the stricter date of 40 working days from the notice, so the claim is never at risk.
Under clause 23.6 the Principal Agent must grant, reduce or refuse the claim within 20 working days of receiving it. Under clause 23.7, silence within that period is treated as a refusal. A deemed refusal is the point at which the contract's dispute resolution provisions become relevant, so diarise that date too.
On Wednesday 1 April 2026 the site agent learns that the structural drawings for level 3, due that day, will not be issued for some weeks. The pour is on the critical path.
Assumptions: Saturdays are not working days, there is no builders' break in this period, and the 2026 public holidays apply: Good Friday (3 April), Family Day (Monday 6 April), Freedom Day (Monday 27 April), Workers' Day (Friday 1 May) and Youth Day (Tuesday 16 June).
Missing the 20 working day notice means you forfeit the right to a revision of the date for practical completion and to any related cost, leaving you exposed to penalties for late completion even where the delay was not your fault.
Whether a forfeiture applies in a particular case can be argued, but this guide does not predict the outcome of any dispute and is not legal advice. Take advice on your own facts if a deadline has passed.
The description above follows the standard JBCC 6.2 conditions. Your signed agreement's own amendments, including any Z clauses, special conditions and contract data, govern over the standard conditions. Read them before relying on any period here. More on the JBCC family is at JBCC contracts.
Sakhani reads your signed contract, including its amendments, and counts the working days from the date of each event you record. It reminds the people responsible before the notice and claim deadlines fall due and drafts the notice for a person on your team to check and send. See how it works or register to try it on a live project.
See every JBCC notice with its clause, period and addressee, or let Sakhani read your signed contract and keep the clocks for you.