Where the period runs from
JBCC and GCC count from the date the payment certificate is issued. FIDIC counts from the Engineer's receipt of your statement, and NEC from the assessment date. The result names the clause so you can check it in your contract data, which often changes the number of days.
Interest on late payment runs from the day after the due date. Take that date to the late payment interest calculator to see what is owed.
Worked example
A JBCC 2018 payment certificate is issued on Wednesday 28 October 2026. With the standard 7 calendar days, payment is due on Wednesday 4 November 2026, which is the local government elections public holiday. Interest runs from Thursday 5 November.